3T/H Boiler Modification

  
                                                                            
      
                                                                            
                                 
                
CV.PANCA WAHANA ENGINEERING in mei 2008 have succeeded to modify 2 boiler unit in PT Vonex Indonesia-Bandung. The Boiler have capacities 3 T/h with diesel fuel fuel. with modified to become  Coal fuel smolder the the boiler more efficient in commercial facet. With calculation of real correct engineering hence after modified by the boiler performa and capacities have experienced of change. Boiler capacities mount, and increase  of quicker boiler pressure so that satisfied PT Vonex with the boiler performance. Hitherto the boiler operate without constraint meaning.