PT. Trie Fashion represent company of loundry textile, where in its production use boiler with capacities 500 kg/h .  Previous of this boiler use diesel fuel or residu. To minimize production cost hence the boiler asked to be modified to become use fuel coal or wood. hence CV Panca Wahana engineering  make design and change sisitem combustion of this boiler by using  fuel  coal or wood. our design with system combustion of Fix Grade at the boiler. which this is system very fitt in with system combustion of  coal fuel smolder and also and wood. Operation of this system very easy. till in this time the boiler work without any constraint.